Location: Corinth, NY

Project Summary:
The Village of Corinth was awarded $1 million in CDBG funds to help construct a new Waste Water Treatment Plant (WWTP). The total project cost was $14,442,000, The project benefited all 2,474 Village’s residents, 1,460, or 59% of whom are low-and-moderate income persons.

Activity:
• _X_ Infrastructure
• __ Economic Development
• __ Public Services
• __ Housing
• __ Acquisition
• __ Other (please describe):

Project Resources – list all sources of funding:
• CDBG $1,000,000
• Clean Water State Revolving Loan Financing (CWSRF) $8,442,000
• NY Water Grants $5,000,000
• Total $14,442,000

Results/Impact:
The project benefited all 2,474 Village’s residents, 1,460, or 59% of whom are low-and-moderate income persons.

Partner engagement
• Village of Corinth
• NYS Office of Community Renewal
• NYS Department of Environmental Conservation
• NYS Department of Health

Project Status: The project is complete

Contact:
Jason Purvis, VP Federal Programs
NYS Office of Community Renewal
518-474-2057